Work continues on Saltmarket Railway Bridge

An aerial view of the Saltmarket Railway Bridge
Saltmarket Railway Bridge Arial photo, from Network Rail

Network Rail’s repairs to the Saltmarket Railway Bridge recommenced on the 5th of January, moving onto stage three of the planned work. Below, you can see a schedule of work for Stage 3 of a total of 5:

DateShift TimesActivities
5th Jan – 8th FebSunday to Friday 07.00 – 18.00Single Lane Closure in place of outer southbound to allow erection of scaffold over the footpath, covering of bridge structure for grit blasting and painting preparation
28th Jan – 8th FebSunday to Friday 18.00 – 00.30Single Lane Closure in place of outer southbound to allow erection of scaffold over the footpath, covering of bridge structure for grit blasting and painting preparation
5th Jan – 8th FebSaturdays 22.00 – 07.00Ballast retention work and on track mechanical preparation and painting of girders
4th Feb – 1st AprMonday to Friday 12.30 – 23.00Steelwork and strengthening works, which will include an element of rivet bursting on each shift
1st Apr – 14th MaySunday to Friday 07.00 – 18.00Painting bridge and then removal of scaffolding and traffic management
Phase Three Schedule of Work

Questions about the work should go to Network Rail, and more details and contact information can be found at https://www.networkrailmediacentre.co.uk/news/improvement-work-set-to-begin-on-glasgow-city-centre-rail-bridge